The Trellix Intelligent Virtual Execution - Server 10.0.0 release requires a reboot for the update to take effect. You can upgrade your IVX appliance to 10.0.0 from release 9.1.0 or later.
Note
You can upgrade Intelligent Virtual Execution - Server appliances to 10.0.0 only if they are standalone nodes. For information on upgrading MVX clusters (MVX Smart Grid), see Upgrading MVX Clusters on the next page.
IPMI and BIOS firmware updates are required for the VX 5500 model. See the section "Upgrading IPMI 3.11 and BIOS 1.9 Firmware for Specific Platforms" below.
Note
After an upgrade to version 10.0.0, certain processes will be in a pending state until new security content is downloaded and installed. See the following section, "Download the security content bundle".